PROJECTS

CURRENT PROJECTS

REPLACE PIPELINE FROM SKIETBAAN RESERVOIR TO GRASPAN WATER PIPES MHLUZI : 560

  • Client : Steve Tshwete Local Municipality
  • Location : Graspan
  • Contract Value : R 52 000 000
  • Duration : 10 months Project

NEW SEWER NETWORK EXT. 2: W23

  • Client : Steve Tshwete Local Municipality
  • Location: Mhluzi Ext 2
  • Contract Value : R 20 000 000
  • Duration : 6 months

NEW WATER NETWORK W23: WIP

  • Client : Steve TshweteLocal Municipality
  • Location : Mhluzi Ext 2
  • Contract Value : R 20 000 000
  • Duration: 6 months

BULK WATER RETICULATION (NODE D) W21

  • Client : Steve Tshwete Local Municipality
  • Location : Mhluzi Ext 23
  • Contract Value : R 5 000 000
  • Duration : 8 months

PLAN & DESIGN SEWER NETWORK (NODE D) W21: WIP

  • Client : Steve Tshwete Local Municipality
  • Location : Mhluzi Ext 23
  • Contract Value : R 7 000 000
  • Duration : 8 months

BULK SEWER & COLLECTION NETWORK

  • Client : Steve Tshwete Local Municipality
  • Location : Dennesig
  • Contract Value : R 15 000 000
  • Duration : 6 months

OUTFALL SEWER PIPELINE FROM GERMAN DEVELOPMENT TO EASTDENE

  • Client : Steve Tshwete Local Municipality
  • Location : Eastdene
  • Contract Value : R 18 000 000
  • Duration : 9 months

UP LADIES RESIDENCE BULK WATER UPGRADE

  • Client : University of Pretoria
  • Location : Pretoria
  • Contract Value : R 12 000 000
  • Duration : 8 months

NEW WATER NETWORK KWAZA W02 : 566

  • Client : Steve Tshwete Local Municipality
  • Location : Hendrina/Kwaza
  • Contract Value : R 2 005 528,5
  • Duration : 6 months

NEW SEWER NETWORK KWAZA W02 : 567

  • Client : Steve Tshwete
  • Local Municipality
  • Location: Kwaza, Hendrina
  • Contract Value: R 2 436 000
  • Duration: 6 months

THE CONSTRUCTION OF BULK SEWER PROJECT A: PHASE 1 – BULK SEWER PIPELINE FROM FINSBURY TO THE INTERSECTION OF R28 AND THIRD ROAD IN PELZVALE

  • Client: Rand West City Local Municipality
  • Location : Randfontein
  • Contract Value : R 46 000 000
  • Duration : 12 months